#6.INSTALLATION & ACCEPTANCE STAGE
During the installation and acceptance stage, the software artifacts, online help, and
initial production data are loaded onto the production server. At this point, all test
cases are run to verify the correctness and completeness of the software. Successful
execution of the test suite is a prerequisite to acceptance of the software by the
customer. After customer personnel have verified that the initial production data load
is correct and the test suite has been executed with satisfactory results, the customer
formally accepts the delivery of the software.






The primary outputs of the installation and acceptance stage include a production
application, a completed acceptance test suite, and a memorandum of customer
acceptance of the software. Finally, the PDR enters the last of the actual labor data
into the project schedule and locks the project as a permanent project record. At this
point the PDR "locks" the project by archiving all software items, the implementation map,
the source code, and the documentation for future reference.